| May 15, 2024 |
Docket 55378 – Document 218694 Detail |
Q1 2024 Large Load Economic Development Report |
The Q1 2024 Large Load Economic Development Report, filed May 15, 2024. This is the earliest report in your list and provides a strong baseline for comparing the scale and pace of Georgia’s later large-load expansion. |
| August 15, 2024 |
Docket 44280 – Document 219685 Detail |
January–June 2024 Grid Investment |
The January–June 2024 Grid Investment Program report, filed in August 2024. This is useful for tracing whether later transmission projects or related grid investments had identifiable predecessors before the major acceleration in large-load growth. |
| August 16, 2024 |
Docket 55378 – Document 219697 Detail |
Q2 2024 Large Load Economic Development Report |
The Q2 2024 Large Load Economic Development Report, filed August 16, 2024. It provides an earlier benchmark for large-load demand and is useful for showing how quickly the pipeline changed over the following two years. |
| November 18, 2024 |
Docket 55378 – Document 220461 Detail |
Q3 2024 Large Load Economic Development Report |
The Q3 2024 Large Load Economic Development Report, filed November 18, 2024. It helps document when major new loads first began appearing in Georgia Power’s formal economic-development reporting before the later expansion of the pipeline. |
| February 17, 2025 |
Docket 44280 – Document 221505 Detail |
February 2025 Grid Investment Program |
The February 2025 Grid Investment Program report. It provides an earlier snapshot of planned and ongoing grid investments and helps establish when specific projects first appeared in Georgia Power’s formal reporting. |
| February 21, 2025 |
Docket 55378 – Document 221545 Detail |
Q4 2024 Large Load Economic Development Report |
The Q4 2024 Large Load Economic Development Report, filed February 21, 2025. It establishes the large-load pipeline at the end of 2024 and provides a baseline against which the rapid growth in 2025–2026 can be measured. |
| May 22, 2025 |
Docket 55378 – Document 222764 Detail |
Q1 2025 Large Load Economic Development Report |
The Q1 2025 Large Load Economic Development Report, filed May 22, 2025. This is a useful starting point for tracing the 2025 growth in major industrial and data-center electric demand. |
| July 9, 2025 |
Docket 56298 Detail |
Updated Load Forecast |
Georgia Power’s open docket for certification of its 2029–2031 All-Source Capacity RFP. It is relevant to the updated load forecast because the amount and timing of projected demand directly drive how much new generation capacity Georgia Power says it must procure. |
| August 15, 2025 |
Docket 44280 – Document 223708 Detail |
August 2025 Grid Investment Program |
The August 2025 Grid Investment Program report. This is useful as a baseline for determining which infrastructure projects were already in Georgia Power’s investment program before later 2026 transmission and large-load developments. |
| August 15, 2025 |
Docket 55378 – Document 223705 Detail |
Q2 2025 Large Load Economic Development Report |
The Q2 2025 Large Load Economic Development Report, filed August 15, 2025. It provides a mid-2025 snapshot of Georgia Power’s large-load development pipeline and allows comparison with later quarters as projects advanced or changed. |
| November 21, 2025 |
Docket 55378 – Document 224615 Detail |
Q3 2025 Large Load Economic Development Report |
The Q3 2025 Large Load Economic Development Report, filed November 21, 2025. It is useful for tracking when large customer projects moved into Georgia Power’s reported pipeline during the period when data-center-driven demand was accelerating. |
| February 11, 2026 |
Docket 55378 – Document 225384 Detail |
Q4 2025 Large Load Economic Development Report |
The original Q4 2025 Large Load Economic Development Report, filed February 11, 2026. It captures Georgia Power’s reported large-load activity at year-end 2025 before the subsequent revised filing. |
| February 16, 2026 |
Docket 44280 – Document 225434 Detail |
February 2026 Grid Investment Program |
The February 2026 Grid Investment Program report. Comparing it with the August 2026 filing can show which grid projects were added, changed in scope, advanced, delayed, or had costs revised during the first half of 2026. |
| February 27, 2026 |
Docket 56002 – Document 225600 Detail |
Grid Investment Plan |
Georgia Power’s 2025 Annual Transmission Update, filed February 27, 2026. This filing is the principal annual update on transmission planning and is useful for tracking new lines, upgrades, project timing, system needs, and changes since the prior transmission plan. |
| March 4, 2026 |
Docket 55378 – Document 225690 Detail |
Revised Q3–Q4 2025 Large Load Economic Development Report |
A revised Q3–Q4 2025 Large Load Economic Development Report, filed March 4, 2026. Because it is a revised filing, it is useful for identifying corrections or updates to Georgia Power’s previously reported large-load pipeline for the second half of 2025. |
| May 15, 2026 |
Docket 55378 – Document 226607 Detail |
Q1 2026 Large Load Economic Development Report |
The Q1 2026 Large Load Economic Development Report, filed May 15, 2026. It provides the first-quarter 2026 snapshot of large-load projects and can be compared with later filings to see changes in customer commitments, projected demand, and development status. |
| August 17, 2026 |
Docket 44280 – Document 227778 Detail |
August 2026 Grid Investment Program |
The August 2026 Grid Investment Program filing. It provides the most recent reporting in this series on Georgia Power’s grid modernization and capital-investment activities, making it useful for identifying newly funded or advancing transmission and distribution projects. |
| August 17, 2026 |
Docket 55378 – Document 227753 Detail |
Q2 2026 Large Load Economic Development Report |
Georgia Power’s Q2 2026 Large Load Economic Development Report, filed August 17, 2026. It reports the status of large-load economic-development activity and is particularly relevant for tracking the growth, timing, and potential system effects of major customers such as data centers. |
| August 17, 2026 |
Docket 55378 – Document 227747 Detail |
Q2 2026 Large Load Economic Development Report |
Another public filing of the Q2 2026 Large Load Economic Development Report was received on August 17, 2026, with a cover letter and report attachments. The PSC webpage shows an erroneous filed date of January 1, 1900, so the received date of August 17, 2026 is the meaningful date to use. |
|
SERTP – Southeastern Regional Transmission Planning |
SERTP Updates (Click the +/- on the right) |
The Southeastern Regional Transmission Planning reference library contains quarterly planning presentations, economic-planning studies, regional transmission assessments, stakeholder materials, and archives. It is useful for identifying projects and constraints that may not appear first in Georgia PSC filings, especially projects affecting multiple utilities or interstate transmission planning. |